General Scope of Project

Complete renovation of 400,000 sq. ft. high school and addition of approximately 35,000 sq. ft.  This project was managed by a Construction Manager and DAVID Construction was responsible for Bid Package 2 General trades package which included site work, demolition, concrete, structural steel, carpentry, doors and hardware, windows, storefronts, finish flooring, specialties and elevator. The project was phased over 2 1/2 years and was completed while the school was in operation.  This project was completed on time and under budget.

Owner

Greater Clark County Schools
Auxillary Services
2710 E. 10th Street
Jeffersonville, IN 47130

Steve Hobgood
(812) 288-4821

Architect

Gibraltar Design
1902 N. Meridian St. Ste 300
Indianapolis, IN 46260
(317) 580-5777

Completion Date

Winter 2010

Construction Cost

$9,451,813